Development Process for 46th Avenue North Sidewalk Improvements
The following schedule is preliminary and will be updated as the project progresses.
Milestone | Estimated Date |
---|---|
15% Design Plans Complete | November 2021 |
60% Design Plans Complete | September 2023 |
100% Design Plans Complete | January 2024 |
Final Design Plans Complete | February 2024 |
Construction Start | September 2024 |
Construction End | May 2026 |