Development Process for 46th Avenue North Sidewalk Improvements

The following schedule is preliminary and will be updated as the project progresses.

Milestone Estimated Date
15% Design Plans Complete November 2021
60% Design Plans Complete April 2022
100% Design Plans Complete February 2023
Final Design Plans Complete June 2023
Construction Start October 2024
Construction End September 2026