Development Process for Anclote Road Roadway and Stormwater Improvements

The following schedule is preliminary and will be updated as the project progresses.

Milestone Date
Preliminary Engineering Report and 30% Plans In progress - July 2023
Final Design August 2023 - July 2025
Construction (Phases to be determined) August 2025 - October 2027
  • September 2021 – Board  of County Commissioners approves funds to complete a Preliminary Engineering Report and 30% plans for this project.
  • November 2021 – Development of Preliminary Engineering Report and 30% plans begins.
  • February 2022 – Topographic survey and geotechnical work are completed.
  • August 2022 – Development of conceptual plans for project design alternatives is scheduled for completion.
  • Fall/Winter 2022 – Project Information Meeting to present design alternatives and receive community feedback.
  • July 2023 – 30% plans and Preliminary Engineering Report scheduled for completion.