Crystal Beach Drainage and Roadway Improvements Development Process
The following schedule is preliminary and will be updated as the project progresses.
Project Schedule for Crystal Beach Drainage and Roadway Improvements
Milestone | Date |
---|---|
Procurement | Complete |
Preliminary Engineering Study and 45% Plans | In Progress |
Final Design | Spring 2024 – Spring 2025 |
Construction Bid Package & Procurement | Spring 2025 - Fall 2026 |
Construction | Spring 2026 - Fall 2027 |
Related Updates
- Living Shoreline – As a separate project, the Crystal Beach community has expressed interest in creating a living shoreline consisting of oyster beds and native wetland plantings. The shoreline will help improve water quality, provide additional habitat and slow shoreline erosion. Further coordination between the County and the community will refine the location, extents and phasing of the project. The County is seeking grant opportunities for funding.