Development Process for for Forest Lakes Blvd. Phase III Roadway Widening Improvements
The following schedule is preliminary and will be updated as the project progresses.
Project Schedule
Last updated: October 2022
Milestone | Date |
---|---|
Begin Study | January 2022 |
Analyze Alternatives | January - September 2022 |
Project Information Meeting | November 2022 |
Select Recommended Alternative | Late 2022/Early 2023 |
Finalize Study | Late 2022/Early 2023 |
Begin Design | Summer 2023 |
Begin Construction | Late 2027 |
Following data collection and review, we will use the comments we receive from local stakeholders and the community to develop Build Alternatives. Once created, we will compare the Build Alternatives against the No-Build Alternative. The results will be presented to the public to allow the community to voice their opinion prior to identifying a recommended alternative. The No-Build Alternative may be recommended if the proposed Build Alternatives cause negative impacts that outweigh the benefits of the improvements.