Lake Shore Estates Roadways and Drainage Improvements Construction Schedule

Use the color-coded phasing map with the specific areas noted below.

(Please contact our Office of Human Rights at (727) 464-4880 or accommodations@pinellascounty.org if you require additional assistance.)

Planning – COMPLETE

  • Preconstruction Meeting – NTP to be Issued
  • Construction Forbearance Period – Administrative Change to Project Time
  • Mobilization
  • Maintenance of Traffic Set Up & Survey of Project

Phase 1 (Yellow) – COMPLETE

  • Erosion Control Installation
  • Water Line Installations
  • Storm Sewer Installations
  • Curb & Gutter / Driveways / Walks Installations
  • Milling
  • Remove Existing Base – Install New Base
  • Asphalt Pavement – Single Lift
  • Restoration – Including Resetting Mailboxes

Phase 2 (Green) – COMPLETE

  • Erosion Control Installation
  • Water Line installations
  • Storm Sewer Installations
  • Curb & Gutter / Driveways / Walks Installations
  • Milling
  • Remove Existing Base – Install New Base
  • Asphalt Pavement – Single Lift
  • Restoration – Including Resetting Mailboxes 

Phase 3 (Orange) – COMPLETE 

  • Erosion Control Installation
  • Sanitary Sewer Installation
  • Water Line installations
  • Storm Sewer Installations
  • Curb & Gutter / Driveways / Walks Installations
  • Milling
  • Remove Existing Base – Install New Base
  • Asphalt Pavement – Single Lift
  • Restoration – Including Resetting Mailboxes

Phase 4 (Blue) – UNDERWAY

Phase 4 (Blue) is expected to be substantially complete before the end of October 2022. 

  • Erosion Control Installation: Complete
  • Water Line Installations: Complete
  • Storm Sewer Installations: Complete
  • Remove Existing Base & Install New Base: Complete
  • Milling / Asphalt Removal: May – November 2022
  • Curb & Gutter / Driveways / Walks Installations: August – November 2022
  • Asphalt Paving: November – December 2022
  • Restoration – Including Resetting Mailboxes: October – December 2022
  • Holiday Shutdown: Dec. 24, 2022 – Jan. 2, 2023

Finalization Phase

The Finalization phase is expected to be substantially complete before the end of January 2023. 

  • Punch List Items: October – January 2023
  • Final Cleanup & Demobilization: January 2023