Process Schedule for the Walsingham Equestrian Park Project

Project ID

004242A

Project Location

Walsingham Equestrian Park

Project Status

Construction: In progress

The Walsingham Equestrian Park Feasibility Study was completed in July 2020. For the Feasibility Study results statement, visit the Community Outreach web page.

Evaluation Phase for Walsingham Equestrian Park Evaluation

The below schedule is preliminary and will be updated as the project progresses.

Milestone Date
Conceptual plan proposal information packet to Walsingham Horseman's Association, Inc. and Kiwanis Horses for Handicapped Foundation of Pinellas, Inc. April 2020
Feasibility Study May 2020 – July 2020
Nutrient Source Tracking Study August 2020 – April 2022
Neighborhood Project Information Meeting TBD based on Nutrient Source Tracking Study data

We will be seeking essential community involvement and feedback throughout this process.