173rd to 176th Ave East Redington Neighborhood Water Main Replacement
Project ID
006168A
Project Location
The neighborhoods surrounding 173rd to 176th Avenues East in Redington Shores and North Redington Beach.
Project Status
Design: In progress
Project Overview
Some of the water mains servicing the neighborhoods around 173rd to 176th Avenue East in Redington Shores and North Redington Beach are reaching the end of their expected life spans. To ensure the continued delivery of drinking water to our customers and reduce the risk of unplanned interruptions, we are replacing sections of these mains. This project will use open-trench construction to replace approximately 11,000 feet of existing galvanized and polyvinyl chloride (PVC) pipes with new PVC lines to increase durability and meet industry standards. We will also be replacing fire hydrants, customer water meters, meter boxes, and service lines.
Project Goals
- Replace existing water mains, meters, meter boxes, and service lines.
- Ensure continuity of service and minimize the risk of line breaks or service interruptions
- Improve public safety through the replacement of existing and installation of new fire hydrants.
Project Location

This project is located in the north Redington Beach and Redington Shores neighborhoods located from 173rd East to Wall Street.
Project Funding
This project is funded by the Pinellas County Water Enterprise Fund.
Anticipated Time Line
Phase | Begin | End |
Design | Late-2024 | Mid-2025 |
Construction | Early-2026 | Early-2027 |
Contact Us
Mohammed Bargothi
Project Manager
Pinellas County Utilities
(586) 565-4360
mbargothi@pinellas.gov