53rd Avenue North Force Main Replacement

Project ID

005582A

Project Location

53rd Avenue N from Duhme Road to just east of Seminole Boulevard in unincorporated St. Petersburg.

Project Status

Construction: In progress

Project Update – March 21, 2025

In order to correct roadway unevenness, crews will be working to improve sections of 53rd Ave. N over the next couple of weeks. Emergency measures have been applied as a short-term fix, which will be modified as time allows for a more aesthetic and sustainable solution. Please adhere to posted signage during this time and use caution when driving in the area.

Project Overview

The existing sanitary sewer force main running below 53rd Avenue N. from Duhme Road to east of Seminole Boulevard is nearing the end of its operational lifespan. This project will use a combination of open trench construction and subsurface directional drilling to replace approximately 2,900 feet of the current 24-inch diameter pipe with 20-inch PVC pipe to increase durability and meet industry standards.

Project Goals

  • Replace aging sanitary sewer force main
  • Reduce risk of sanitary sewer main breaks and wastewater discharge
  • Improve public safety

Project Location

This project is located on 53rd Avenue N from Duhme Road to the east of Seminole Boulevard in unincorporated St. Petersburg.

Project Funding

This project is funded by Pinellas County’s Sewer Renewal and Replacement Fund.

Anticipated Project Timeline

PhaseBeginEnd
DesignAugust 2024November 2024
ConstructionDecember 2024July 2025
On-site construction typically takes place between the hours of 7 a.m. and 5 p.m., Monday through Friday, and occasionally on Saturdays. The construction schedule may vary due to unforeseen circumstances such as weather.

Contact Us

Shannon Ransom
Project Manager
Pinellas County Utilities
(727) 464-6861