North Pinellas County Reclaimed Water Booster Pump Station

Project Location

Community: Palm Harbor - Fox Chase area Project Site: Southwest corner of the intersection of County Road 70 and Belcher Road in unincorporated Palm Harbor. See project map for details.

Project Status

Construction: In progress

Alderman Road will be closed with detours starting June 23, 2025. The road closure is scheduled to reopen by mid-July, prior to school resuming.

Project Description

Pinellas County is constructing a Reclaimed Water Booster Pump Station in North County to improve water pressure in the reclaimed water system. The project includes installing a new 24-inch reclaimed water main and other related infrastructure to ensure customers consistently receive reclaimed water at the County’s standard pressure of 50 psi.

Project Map

This map outlines the area where construction will take place from the southwest corner of the intersection of County Road 70 and Belcher Road in unincorporated Palm Harbor.

Project Goals

  • Boost reclaimed water pressure to meet 50 psi service level
  • Improve reliability and delivery of reclaimed water to customers
  • Comply with regulatory and hydraulic performance
  • Prepare North County reclaimed water system for future demand

Project Phases & Timeline

PhaseBeginEnd
DesignCompletedCompleted
ConstructionJune 23, 2025Summer 2026*
* Construction duration estimated based on document details and standard timelines. Specific dates may vary depending on permitting and weather conditions.

Detour map

This map shows the detour routes for the Alderman Rd. reclaimed water booster pump station construction.

Project Funding Source

This is a Capital Improvement Project funded by Pinellas County’s Sewer Renewal and Replacement Fund.

Contact us

William (Bill) Peters
Project Manager
Pinellas County Utilities
(727) 464-8435
wpeters@pinellas.gov