Expect construction noise Nov. 30 through Dec.
Construction of the parking garage structure, including pile driving, will begin Nov. 30 and last approximately four weeks. Work will take place between 7 a.m. and 4 p.m., Monday through Friday. Construction noise will louder during this period.
Initial pile driving has been completed.
Construction continues on the building foundation and underground utilities.
Expect construction noise Aug. 31 through Sept.
Construction of the foundation, including pile driving, will begin August 31 and last approximately four weeks. Work will take place between 7 a.m. and 4 p.m., Monday through Friday. This will be one of the noisier phases of the two-year project.