54th Avenue North Road Force Main Replacement
Last updated on
Project ID
005584B
Project Location
54th Avenue North from the west bank of St. Joe's Creek to 74th Street North in St. Petersburg.
Project Status
Design: Completed
Project Overview
The existing sewer main running below 54th Avenue North from just west of St. Joe’s Creek to 74th Street North is nearing the end of its expected lifespan. This project will use a combination of open trench construction and subsurface directional drilling to replace approximately 1,295 feet of the current 24-inch diameter concrete pipe with pipe of the same diameter in PVC.
Project Goals
- Replace aging sanitary sewer force main
- Reduce risk of sanitary sewer main breaks and wastewater discharge
- Improve public safety
Project Location

This project is located on 54th Avenue North from the west bank of St. Joe’s Creek to 74th Street North in St. Petersburg.
Project Funding
This project is funded by Pinellas County’s Sewer Renewal and Replacement Fund.
Anticipated Project Timeline
| Phase | Begin | End |
| Design | Late 2023 | Early 2026 |
| Construction | Early 2027 | Early 2028 |
Contact Us
Have questions about this project? Call (656) 262-7169 for more information.