Sawgrass Lake Park Boardwalk & Tower Rehabilitation

Project ID

004452C

Project Location

7400 25th St. N., St. Petersburg, FL 33702

Project Status

Construction: Completed

Project Overview

Pinellas County Parks and Conservation Resources and Public Works undertook a project to rehabilitate the existing boardwalk and tower within Sawgrass Lake Park as part of the Countywide Annual Boardwalk, Fishing Pier and Observation Tower Improvements contract.

The contractor, Bayshore Construction, Inc., rehabilitated the existing boardwalk facilities. Construction activities were completed in phases and coordinated with Parks and Conservation Resources staff to reduce the impact on visitors.

Sawgrass Lake Boardwalk & Tower Rehabilitation project phasing

Project Timeline

Phase A: July 2023 – March 2024: COMPLETE
Phase B: November 2023 – March 2024: COMPLETE
Phase C: March 2024 – August 2024: COMPLETE

Project Funding

This project is supported by the Penny for Pinellas.