Tarpon Woods Structure Rehabilitation

Project ID

004207E

Project Location

Tarpon Woods Boulevard, between Oak Ridge Dr. and Bridlewood Blvd.

Project Status

Construction: Completed

Project Overview

This project removed and replaced stormwater structures and pipes that needed repair and restored the roadway.  The location of construction was along Tarpon Wood Boulevard between Oak Ridge Drive and Bridlewood Boulevard.

Project Location

map of road closure planned for Tarpon Woods Blvd.

Project Schedule

  • Construction: Early October – Nov. 5, 2026 (Complete)

Community Outreach

Preconstruction letters were sent to affected property owners ahead of construction.

Project Funding

This projected is supported by the Penny for Pinellas.

Contact Us

Cally Wharry
Construction Project Manager 
Public Works / Construction
22211 US Hwy 19 N., Clearwater, FL 33765 
(727) 464-8886
cwharry@pinellas.gov

Travis Gennell 
Design Project Manager 
Public Works / Capital Improvements 
14 S. Ft. Harrison Ave., Clearwater, FL 33756 
(727) 464-3486
tgennell@pinellas.gov