Water Main Relocation for US-19 Roadway Improvements
Project ID
001522A
Project Location
US-19 near Evans Road in Clearwater
Project Status
Construction: In progress
Project Overview
Pinellas County Utilities is relocating a 36” transmission water main and an 8” distribution water main to accommodate road improvements being made on US-19 by the Florida Department of Transportation. Since this work is happening on the east and west sides of US-19 near Evans Road, our contractor will be staging construction equipment and materials at the County-owned property off Summerdale Drive on Mario Way in Clearwater. Residents in that area may notice work truck activity Monday through Friday, between 7 a.m. and 5 p.m. during project construction.
Anticipated Timeline
Construction is slated for December 2026 and should last approximately 8 months.
Project Funding
This project will cost $6,093,995.33 using Pinellas County Utilities Water funds.