13th Street/Sands Point Drive Bridge Replacement

Project ID

000971A

Project Location

13th Street S., near 3rd Avenue S. in Tierra Verde

Project Status

Design: In progress

Project Overview

Pinellas County is planning for the replacement of the 13th Street Bridge as part of an ongoing effort to maintain and operate a network of more than 140 bridges.

The 13th Street Bridge was originally constructed in 1957 and repaired in 1992. Preliminary engineering reports conducted in 2018 and 2021 show the existing bridge is nearing the end of its useful life and requires complete replacement. The bridge provides the only access to the island community of Paradise Key, a part of Tierra Verde.

The existing bridge is approximately 120-feet-long with three equal spans of 40 feet. The bridge has an overall roadway width of 37 feet, providing two 12-foot lanes and 3.75 feet of sidewalks on both sides.

Pinellas County is proposing a 180-foot-long bridge with three equal spans of 60 feet to help improve water flow and reduce scour through the canal. The proposed bridge will have an overall width of 49 feet, providing two 12-foot lanes, shoulders, and 6-foot sidewalks on both sides.

Project Location

13th Street Bridge Project location map

Anticipated Project Schedule

Design Start: Summer 2022
Design End: Spring 2024
Construction Start: Spring 2025
Construction End: Summer 2027

Project Status

  • August 18, 2022: Design phase begins
  • January 2021: Preliminary Engineering Report Phase II completed
  • December 2018: Preliminary Engineering Report Phase I completed

Community Outreach

Pinellas County plans to hold a neighborhood public information meeting after completion of the 30% design phase. The meeting is expected to be in Summer 2023. The latest updates can be found on this webpage.

Contact Us