Baypointe Stormwater Conservation Area Development Process
The following schedule is preliminary and will be updated as the project progresses.
Project Schedule
Milestone | Date |
---|---|
Clean Up | March 2020 – May 2020 |
Survey | May 2020 – May 2021 |
Virtual Project Information Meeting for brownfield support | Sept. 29, 2020 |
First Hearing for brownfield designation | Dec. 15, 2020 |
Second Hearing for brownfield designation | Jan. 12, 2021 |
Sampling for refinement of contamination assessment for FDEP Brownfield Program | June 2020 - September 2023 |
Alternative Design Development | January 2021 - March 2023 |
Project Information Meeting | March 21, 2023 |
30% plans | June 28, 2023 |
60% plans | Winter 2023/2024 |
90% plans | Spring 2024 |
100% plans | Summer 2024 |
Bid Project | Summer/Fall 2024 |
Construction Start | Winter 2024/2025 |
Construction Complete | Winter 2026 |
Construction may occur on only half of the site at a time so that the remainder can be open to the public.