Baypointe Stormwater Conservation Area Development Process

The following schedule is preliminary and will be updated as the project progresses.

Project Schedule

Milestone Date
Clean Up March 2020 – May 2020
Survey May 2020 – May 2021
Virtual Project Information Meeting for brownfield support Sept. 29, 2020
First Hearing for brownfield designation Dec. 15, 2020
Second Hearing for brownfield designation Jan. 12, 2021
Sampling for refinement of contamination assessment for FDEP Brownfield Program June 2020 - September 2023
Alternative Design Development January 2021 - March 2023
Project Information Meeting March 21, 2023
30% plans June 28, 2023
60% plans Winter 2023/2024
90% plans Spring 2024
100% plans Summer 2024
Bid Project Summer/Fall 2024
Construction Start Winter 2024/2025
Construction Complete Winter 2026

Construction may occur on only half of the site at a time so that the remainder can be open to the public.