Baypointe Stormwater Acquisition/Park Development Process

The following schedule is preliminary and will be updated as the project progresses.

Project Schedule

Milestone Date
Clean Up March 2020 – May 2020
Survey May 2020 – May 2021
Public Zoom Meeting for brownfield support May 2021 – May 2022
First Hearing for brownfield designation May 2022 – December 2022
Second Hearing for brownfield designation January 2023 – June 2024
Preliminary stormwater study completed February 2021
Sampling for refinement of contamination assessment for FDEP Brownfield Program June 2020 - Spring 2022
Alternative Design Development Spring - Summer 2022
Public Meeting Fall 2022
60% plans Winter 2022/2023
90% plans Summer 2023
100% plans Fall 2023
Bid Project Winter 2023/2024
Construction Start Spring 2024
Construction Complete Fall 2025

Construction may occur on only half of the site at a time so that the remainder can be open to the public.