Indian Rocks Road Culvert Replacement at Adrian Avenue

Project ID

90019Y3

Project Location

Indian Rocks Road, south of Adrian Ave.

Project Status

Design: In progress

Project Overview

The objective of this project is to replace the culvert across Indian Rocks Road, south of Adrian Avenue in Largo that overtopped and caused a failure to the roadway shoulder and adjacent seawall after the storm surge from the hurricanes in 2024.

Project Location

Map of project area along Indian Rocks Road, south of Adrian Ave.

Anticipated Schedule

  • Design: Early 2026 – Late 2027
  • Construction: Summer 2028 – Late 2028

Community Outreach

A project information meeting is planned to be scheduled ahead of construction.

Project Funding

This project is supported by funding from the Federal Highway Administration and the Penny for Pinellas.

Contact Us

Scott Baird, CPM
Project Manager
Public Works / Capital Improvements
14 S. Fort Harrison Ave., Clearwater, FL 33756
(727) 464-8935
sbaird@pinellas.gov