Mehlenbacher Road Sidewalk Improvements
Project ID
001976A
Project Location
Mehlenbacher Road, on north side from Indian Rocks Road to the Pinellas Trail, and on the south side from Indian Rocks Road to west of Dolphin Drive, Belleair Bluffs
Project Status
Construction: Not started
Project Overview
Pinellas County is proposing sidewalk and drainage improvements on Mehlenbacher Road. The project consists of ADA-compliant sidewalks, curb ramps and driveways, along with drainage improvements to reduce flooding and inflow into the sewer system.
The sidewalk and drainage improvements on the north side of Mehlenbacher Road are from Indian Rocks Road to the Pinellas Trail, and on the south side from Indian Rocks Road to west of Dolphin Drive. ADA-compliant sidewalk, curb ramps and driveways will also be constructed at the intersection of Indian Rocks Road and Mehlenbacher Road.
Project Location

Tentative Project Timeline
- Design Start: Winter 2017
- Design End: Winter 2022
- Construction Start: June 2023
- Construction End: August 2024
Community Outreach
- December 10, 2018: Pinellas County held a project information meeting open house at the Belleair Town Hall to provide information about the proposed sidewalk improvements and to answer questions.
The latest project updates can be found on this web page.
Contact Us
John Carpenter, P.E.
Project Manager
Public Works / Capital Improvements
14 S. Ft. Harrison Ave., Clearwater, FL 33756
(727) 453-3350
jcarpent@pinellas.gov