McMullen Booth Road Bridges

Project Overview

The objective of this project is to widen both the northbound bridge and southbound bridge on McMullen Booth Road over Tampa Road. The existing bridges include simple span approaches that use prestressed concrete beams on hammerhead piers, however, the main span over Tampa Road consists of tabletop hammerhead piers that utilize prestressed concrete beams with dapped ends.

The existing bridge typical section consists of two 12-foot travel lanes, one 6-foot inside shoulder, and one 10-foot outside shoulder. The proposed widening will add one 12-foot travel lane to the existing bridge in each direction. The proposed bridge typical section will accommodate three 12-foot travel lanes, and two 10-foot shoulders.

Project Location

McMullen Booth Road Bridge project location map, above Tampa Road

Anticipated Schedule

  • Design: Summer 2027 – Summer 2029
  • Bidding: Summer 2029 – Late 2029
  • Construction: Early 2030 – Early 2032

Community Outreach

Check here for the latest information on meetings with the community.

Project Funding

This project is supported by the Penny for Pinellas.

Contact Us

Arturo MartinezP.E.
Project Manager
Public Works / Capital Improvements